So, you just saw an ad for some new must-have machine that’s on your wish list. If you’re a heavy iron addict like me, you know that paying for the machine is the least of your concerns. Before I hand over the cash I already have a rigging and transportation plan in place to move it from the seller’s location to my shop.
In this post, I’ll discuss how I plan the rigging and transportation of a new machine using a real-world example: Moving my 1970 American Pacemaker engine lathe.

Before Purchasing: Knowing and Assessing My Limitations
Dirty Harry said “A man’s gotta know his limitations.” The first step of a rigging plan is determining whether my capabilites are adequate for the move and how I can use them. There are numerous places I could begin, but I like to take a top-down approach. The top, in this case, is the manufacturer’s written instructions.
Most machine tool manufacturers publish rigging information in the operating manuals of their machines. I begin by studying them carefully and comparing the instructions with my equipment. Many times, the instructions will include an illustration of the recommended way to lift the machine, along with a basic equipment list. The operating manual should also list the weight of the basic machine, plus accessories.
Here are the rigging instructions for my machine, an American Pacemaker 14″ x 30″ “Style B” engine lathe:
With the rigging instructions in-hand, I asked myself: Am I capable of safely performing this rig? If so, what equipment will it take to safely move and rig this machine, following the manufacturer’s instructions as closely as possible?
I decided that I had sufficient experience, but did not have the right equipment. However, a survey of available options concluded that the equipment could be rented at a reasonable cost. The job was on!
Transportation: The Clock Starts Ticking
Transportation was the first area to consider. I decided this was outside my capabilities and renting appropriate equipment did not have a sufficient return as compared to hiring a trucking company. I contacted a trucking company based on the seller’s recommendation to set up a delivery date. From now on, I’m on a schedule and the plan needs to reflect this.
Rigging Day – ASAP: Ordering and Preparing the Equipment
With a delivery date set with the trucking company, everything from here out is on a timeline. During my initial limitations assessment I determined my forklift was not sufficient to lift the machine. However, a few quick phone calls located a 12,000 lb. forklift at a local forklift rental company.
Forklifts are rated by a combination of lifting capacity and load center. During my inspection of the machine I roughly determined the center of gravity to be 24″ from the farthest protrustion on the operator’s side of the machine. Adding 6″ to provide sufficient clearance results in a 30″ load center. My forklift is rated for 8,000 lbs. at a 24″ load center, or 6,400 lbs. at 30″. My forklift would tip over before the 8,000 lb. machine was off the trailer! The forklift I settled on had a capacity of 9,600 lbs. at 30″ load center. Capacity to spare is always a good thing!
In addition, I needed a rigging sling and pins to install in the rigging holes on the machine. I decided on custom-made continuous synthetic slings and 4130 bar stock, both of which I ordered and received promptly.
Finally, I needed a way to move the machine once inside the shop. During the initial limitations survey, I found a local rental house had toe jacks and machinery skates of sufficient capacity. I reserved these well in advance.
Rigging Day – 2: The Machine is Picked Up
Two days before the rigging day the trucking company called to say the machine was on a truck and headed my way. I confirmed the arrival date and time. While it is a good idea to be prepared as far in advance as possible, I didn’t want to rent the equipment before the machine was on a truck. As it turned out, this was good planning on my part. The arrival date was pushed back three times due to trucks failing to pick up the machine at the warehouse. Even after pickup, the delivering truck was delayed in travelling to my shop.
Move Day – 1 Prepare the Equipment and Shop
I scheduled the arrival of the toe jacks, machinery skates and forklift a full day in advance of the scheduled delivery date. While this may seem like excessive, it is better to pay a little more than have the truck show up while you’re still waiting for equipment!
During this time I also prepared the shop by making a path for the new machine and doing general cleaning.
The forklift on the left is my 8,000 lb. machine. The Yale on the right is the rented 12,000 lb. machine:

With all the equipment on-site and the shop ready, I made one final preparation. Using the operating manual as a guide, I marked the forklift forks with a soapstone to show the maximum load center at which I could safely pick up the machine. Running an unfamiliar machine I wanted to be sure I was within its capacity.
In part two I’ll cover rigging the machine and the after-action report.